Commercial Permit Process
This section will outline and explain the City of Spokane’s commercial permit process. Most projects that require a permit will generally fall under one of two categories. The first category is remodels and tenant improvements. The second category is new construction, additions, and changes of use. Remodels and tenant improvements projects generally do not have to submit a drainage plan or an erosion and sediment control plan. The second category usually does have to submit a drainage plan and erosion and sediment control plan. Both categories require the applicant to fill out the Commercial Building Permit.
Under either permit category, a pre-development conference is usually conducted between the applicant and city officials. Furthermore, an intake meeting is required for all new construction, additions, and changes-of-use. After the applicant has submitted his or her application, the City of Spokane will review the application and decide on whether to issue a permit.